Jenny Creek

OLYMPUS DIGITAL CAMERAJENNY CREEK RESTORATION PROJECT

  • Approximately .7 miles of creek damaged – due to extensive Off Highway Vehicle use
  • Close to Rollins Pass Road – Scroll down to see map
  • Joint Effort $180,000 total funding
    • U.S. Forest Service – Project lead and funding source
    • Boulder Flycasters – Funding and in kind labor
    • Colorado Parks and Wildlife – Funding through OHV grant program
  • SCHEDULE – Start Spring 2014 – Complete Spring 2015
  • Tree Cutting  June 15-July 15
    • Harvested trees to be used for stream restoration
  • Reroute and Barricades  July 15-August 15
    • Permanently reroute traffic away from Jenny Creek
  • Jenny Creek Restoration  September 1 – September 30