On May 15, Frank Selto and I joined Corey Engen (Flywater), Blair Vajda (Walsh), Ben Swigle (CPW) and Chris Carroll (USFS) for a final inspection of the USBC project. All the construction looked very good. Follow up work needed:
Moffat area: seeding, erosion control matting, and willow staking on the creek bank: – Flywater
Moffat area: willow cutting for stream bank (200) – Boulder Flycasters
Moffat area: willow cutting and restaking in USFS area (30?) – Boulder Flycasters
Jumbo Mountain area: rough-in 4 access points – Flywater
Jumbo Mountain area: willow staking – perhaps 20 if we think necessary.
Once we are notified the contractor is going to the site for seeding, we’ll be asking for 10 volunteers for a day of willow cutting and staking – should have 10 days or more lead time.