Drove through the rain to attend a project meeting for Upper South Boulder Creek today
Attendees from Flywater, Walsh, CPW, Denver Water, USFS and BFC
Design 75% complete – did approximately 20 cross sections of the two sites
Permitting on pace to be granted by 10/1 (Notification to proceed)
Site prep starting now – Fuel Cells and Excavators on site next week – start staging rock to areas of need.
Construction should complete by 1st week of November
Contractor will reseed areas as equipment is moved out.
BFC to replant willows from cuttings next spring – before leaf out. Will need volunteers then (10 or more).